D54 Project Reviews – August 2026
MEG: Christina Lake
Submitted: February 2026
Reporting Period: January 1 – December 31, 2024
Operational Updates
Achieved average bitumen production of 102,012 bbl/day and steam-oil-ratio (SOR) of 2.39 in 2024
Commenced production and incremental drilling from Well Pad MC and drilling from Well Pad MD/MH
Suspended 16 SAGD production wells, 1 SAGD injection well, and 13 infill production wells
Plans
Execute a turnaround of the Phase 2B central processing facility in Q2 2025
Complete ties ins for a third de-oiling train, and fifth OTSG in Phase 2B
Commence production from Well Pad MD/MH and drilling on Well Pad AJ
Submit applications for Wells Pads/ Patterns MM and ML, and the addition of a Carbon Capture Plant
PetroChina Canada: MacKay River
Submitted: January 2026
Reporting Period: January 1 to December 31, 2024
Operational Updates
Achieved average production of 9,691 bbl/d and average SOR of 5.76
New infill well pairs AF11 and AF12 converted from circulation to SAGD operations by February 2024
NCG co-injection continued in select well pairs and reached peak rate of 30 co-injecting wells in early 2024, then stabilized with 26 co-injecting wells with optimized rates
Gas Cap Pressurization: NCG Injection & Co-Injection
Typical NCG co-injection rates range from 2,400 to 4,100 Sm³/d per well with cumulative NCG co-injection of approximately 98,362 e³Sm³ by December 2024
Expanded NCG co-injection network to 26 well pairs until December 2024
Total produced gas in 2024 corresponded to 14% of the coinjected volumes
Plans
Well Pad AB expansion to support new well pairs in late 2025
Submit applications for annual water withdrawal volume reduction and additional drainage boxes
Consider new infill wells for pads AF and AB
Complete plant turnaround in 2026
Source: Alberta Energy Regulator
Please note that the Alberta Energy Regulator (AER) transitioned to a new protocol in 2021 under which all D54 project reviews submitted by or before June 30th of a given year will be posted during the first quarter of the following year. Summaries for 2-3 project reviews per month will be featured in this publication over the course of a given year once they become available. All available presentations can be viewed online by clicking the source link.
DOB Energy Articles of Note – August 2026
CanAsia
“CanAsia To Sell Sawn Lake Heavy Oil Project” – CanAsia announced that it has entered into a definitive agreement with an arm’s length Alberta corporation that has agreed to acquire all its issued and outstanding shares of Andora Energy Corporation. (August 17, 2026)
Cenovus
“Cenovus Surpasses 1-Million-Boe/d Milestone” – The company reported average Q2 2026 production of 970,000 boe/d, including record oilsands production of over 786,000 bbls/d. (August 4, 2026)
“Focus On Turnaround Efficiency Paying Off for Integrated Oilsands Operators” – Cenovus CEO noted that planned turnarounds for Q3 2026 have been shortened by nine days, which reduces the expected production loss by over 700,000 bbls. (August 6, 2026)
CNRL
“Record-Breaking Quarter for Canadian Natural” – Total production reached 1.677 million boe/d in Q2 2026, up 256,000 boe/d or 18 percent from Q2 2025. (August 6, 2026)
“CNRL Growth Projects Remain on Hold Until Trilateral MOU Finalized” – CNRL has approximately 340,000 bbls/d of medium- and long-term growth projects planned that remain on hold. (August 6, 2026)
“Charlie Lake Consolidation About Cost Savings, Says CNRL” – CNRL CEO noted that recent acquisitions were driven by an opportunity to cut operating costs in the Peace River Arch area. (August 7, 2026)
Imperial
“Imperial Kearl Turnround Completed Ahead of Schedule” – Imperial’s Kearl 1 turnaround was underbudget and the company reported strong Q2 2026 production of 257,000 bbls/d. (August 4, 2026)
IPC
“International Petroleum Seeing Positive Early Results at Blackrod” – IPC’s CEO reported that Blackrod Phase 1 SAGD is "looking very positive" after achieving first oil ahead of schedule and on budget. (August 5, 2026)
Rubellite
“Rubellite Capex to Support Longer-Term Goals, Including EOR In the Clearwater” – The company forecasts total exploration and development spending of $125–$130 million in 2026. (August 11, 2026)
“Rubellite Completes Asset Swap” – The company completed an asset swap transaction that doubled its working interest in its Marten Hills Clearwater assets from 30 to 60 percent. (August 11, 2026)
Strathcona
“Strathcona’s Operating Earnings Surge on Higher Oil Prices” – The company reported Q2 2026 production of 117,022 boe/d, noting a two percent improvement at Cold Lake. (August 7, 2026)
Suncor
“Integrated Model Pays Off for Suncor in Second Quarter” – Suncor broke financial records in Q2 2026 driven by higher prices and strong downstream refinery performance. (August 5, 2026)
“Suncor Wants Certainty on Trilateral MOU Before Changing Growth Plans” – Suncor announced plans to increase upstream production by 100,000 bbls/d by 2028 and to increase Firebag SAGD production from 250,000 bbls/d to 700,000, bbls/d. (August 5, 2026)
“Wet Spring Takes Bite Out of Suncor Mining Production” – Torrential rains in northeast Alberta in Q2 2026 resulted in losing up to 60,000 bbls/d of oilsands mining production. (August 6, 2026)
Other
“Iran War Created Price Volatility for Integrated Oilsands Operators in Second Quarter” – Executives discuss war impacts, noting an estimated nearly three million bbls/d of refining capacity in the Middle East has been shut due to attacks and a lack of viable export outlets. (August 10, 2026)
“Sulphur Sales Providing a Revenue Boost for Some Canadian Operators” – The war in Iran and the closure of the Strait of Hormuz has taken around a quarter of global sulphur supply off the market, resulting in sulphur prices rising by approximately 70 percent, providing a material revenue boost for some gas and oilsands operators. (August 10, 2026)
“Oil Producers Target Late 2027 For Pathways Carbon Capture Decision” – The proposed Pathways project is a CO2 transportation pipeline and storage hub that could reduce greenhouse gas emissions from Canadian oilsands production and is a key piece of a non-binding agreement signed earlier this year by the province of Alberta and the government of Canada. (August 19, 2026)
“Alberta Royalty Changes Coming to Spur Greenfield Oilsands Development” – Premier Smith said that the government has been meeting with major oilsands operators and associations like the Energy and Producers Association of Canada (EPAC) to determine what a new royalty structure could look like and that any new oilsands royalty structure is unlikely to resemble past models that drove initial oilsands development. (August 25, 2026)
“Venezuela Renaissance Series, Part 1 – A Potential Threat to Canada” – The first in a three-part series is to better understand the potential of Venezuelan oil production to rebound, its negative impact on the Canadian oil industry, and what Canada should do to mitigate the risk. (August 31, 2026)
Source: DOB Energy
Technical Publications of Note – August 2026
Production
JPT-0826-0015: Multiphase Pump Solution Deployed in World’s Deepest Subsea Heavy Oil Field
SPE-234835-MS: Deep Geothermal Steam Generator Well: Packer-Isolated Completion for High-Viscosity Oil Recovery
Research
SPE-224322-PA: Machine Learning–Enhanced Analytical Modeling of In-Situ Combustion with Experimental Evaluation of Carbonate Decomposition and Mineral/Gas CO2 Interactions
SPE-235214-MS: Mechanistic Evaluation of Polymer Flooding in Moderate Salinity Reservoirs with Viscous Fluid: Coupling Rheology, Mobility Control, and Displacement Dynamics
SPE-236601-PA: Experimental and Numerical Investigation on Deep High-Pressure Vertical-Horizontal Well Channel-Steam-Assisted Gravity Drainage in Heavy Oil Reservoirs
Reservoir Engineering and Development
SPE-234670-PA: Subcool Optimization in Sandpack for Solvent-Assisted Steam-Assisted Gravity Drainage with n-Butane
SPE-234831-MS: Best Practices in Developing Small Heavy Oil Fields
SPE-234838-MS: Early Phase Crestal Development Strategy: Challenges in Heavy Oil Reservoir Management and the Way Forward, Case Study – Onshore Niger Delta Field
SPE-235055-MS: Assessing the Impact of Well Spacing on Oil Recovery in Polymer Flooding: A Niger Delta Perspective from Reservoir Simulation
SPE-235198-MS: Integrating Recovery Technology Selection and Fiscal Regime Sensitivity in the Economic Evaluation of Heavy Oil Fields
SPE-235213-MS: Economic Analysis and NPV Optimization of Control Parameters for Gas Injection and Polymer Flooding, with Low Salinity Post Water Flush for Heavy Oil Recovery in Niger-Delta Reservoir
SPE-235215-MS: Comparative Simulation Study of CO2 and N2 Foam Injection for Mobility Control in a Heavy Oil Reservoir, Niger Delta
SPE-236593-PA: Mitigating Clay Sensitivity in Heavy Oil Recovery: A High-Intensity In-Situ Combustion Strategy with a Case Study of Block J10, Shengli Oilfield
Source: OnePetro Oil & Gas Technical Library
Regulatory Applications of Note – August 2026
Baytex
1962419: Baytex applied for an enhanced oil recovery (EOR) pilot project using class II water injection within the Peace River Oil Sands Area 2. The pilot’s objective is to determine and quantify waterflood efficacy in the Dawson area given increased crude oil viscosity relative to other reservoirs currently under waterflood.
Caltex
1962354: Caltex submitted a pre-drill application to expand the scheme area and drill four polymer injection wells in the Upper Sparky Member of the Lower Grand Rapids.
CNOOC
1962217: CNOOC requested approval to modify the subsurface well plan and drainage area for Kinosis Pad 3.
1962345/348: CNOOC submitted applications to drill additional brownfield SAGD wells at Long Lake Pads 12 and 6N.
Greenfire
1962255: Greenfire requested approval to change the well orientation and extend the horizontal lengths beyond the approved drainage area at the Hangingstone Expansion Project.
Headwater
1962321: Headwater requested approval to continue the short-term gas injection program which allows for injection of Clearwater solution gas from the 08-34-074-25W4 oil battery when gas conservation is unavailable.
Obsidian·
1962448: Obsidian requested approval to expand the scheme area and add eight additional water injection wells to the Spirit River Formation.
Spur
1962232: Spur submitted a proposal to develop the McMullen Thermal Pilot Project for a pilot-scale bitumen recovery scheme in the Athabasca Oil Sands Area targeting the Wabiskaw Formation.
Suncor
1962317: Suncor requested approval to integrate the Lewis Project with existing infrastructure at its oil sands base plant to reduce costs, improve operational efficiency, and reduce environmental impact.
Source: Alberta Energy Regulator